Reserve fund investments $150,000 as of October 31, 2026
Items in the plan by fiscal year, with the planned cost from the study and what has been spent
Year
Items in the plan
Planned (from the 2024 study)
Spent
2024
Hallway carpet, all floors · Done
$38,500
$61,840
2025
Parkade drain repair · DoneUnplanned repair - not in the study
Boiler, domestic hot water · Done
$14,200
$48,366
2026 this year
Roofing, Building A · UnderwayPart of Roof replacement, Building A
Eavestrough and downspouts, Building A · UnderwayPart of Roof replacement, Building A
Elevator door operator · Approved to go ahead
$169,800
—
2027
Asphalt paving, parking lot · Planned
Lobby furniture · Dropped
Garbage enclosure gate · PlannedAdded after the study
$64,000
—
2028
Exterior painting, trim and doors · Planned 2026, now 2028
Intercom and entry system · Planned
$51,400
—
2029
Fire alarm panel · Planned
$18,500
—
2030
Make-up air unit · Planned
$27,800
—
2031
Nothing planned
—
—
2032
Balcony membranes · Planned
$88,000
—
2033
Nothing planned
—
—
Next reserve fund study due March 2029
The reserve fund year by year
Study forecast figures are the study's own year-by-year table as written in 2024, inflation included and each item in the year the study gave it; the plan table above shows each item where it now sits, priced in the study's dollars, so the two planned figures for a year can differ. Whole dollars.
The reserve fund year by year: contributions paid in, spent and the closing balance, the study forecast beside the actual where one is in
Year
Contributions paid in
Spent
Closing balance
Study forecast
Study forecast
Actual
Study forecast
2024
$72,000
$52,000
$61,840
$404,700
2025
$75,000
$28,000
$48,366
$457,800
2026 this year
$75,000
$175,000
—
$364,700
2027
$78,000
$69,900
—
$378,300
2028
$78,000
$57,800
—
$404,200
2029
$81,000
$21,400
—
$470,100
2030
$81,000
$33,200
—
$525,000
2031
$84,000
$12,600
—
$604,300
2032
$84,000
$108,200
—
$589,200
2033
$87,000
$26,900
—
$658,100
A dash means the figure is not in yet. Spent (actual) is what Hometime's tracked work billed to the reserve fund that year. The contributions actually paid in are not reported here yet. The actual closing balance is not reported here yet.
What has changed
The board approved Elevator door operator to go ahead · November 1, 2026
Work has started on Roofing, Building A · October 7, 2026
The board approved Roofing, Building A to go ahead · September 15, 2026
The board approved Eavestrough and downspouts, Building A to go ahead · September 15, 2026
Moved Exterior painting, trim and doors from 2026 to 2028 because the roof comes first and the trim is in fair condition · September 7, 2026
Dropped Lobby furniture from the plan because the board chose to keep the furniture it has · August 13, 2026
Boiler, domestic hot water is done · October 2, 2025
Parkade drain repair is done · May 29, 2025
Unplanned repair: Parkade drain repair · April 21, 2025
Hallway carpet, all floors is done · September 20, 2024
Roof replacement, Building A
The work is under way and on track. Expected finish: December 2026.
3 of 7
Steps done
Hometime's plan has 7 steps; the key dates are shown below
3
Key dates
Shown below
2
Still to work out
1 listed below; Hometime is working out the other one and will post it here when settled
Key dates
Board approves the roofing quoteSeptember 14, 2026· done
Building permit issuedSeptember 28, 2026· done
Final inspection and warranty registeredDecember 14, 2026· still open
Latest update
Hometime · November 12, 2026 On track
The east half is finished and passed the contractor's own inspection. The west half started on Monday. Weather permitting, the crew expects to finish in about three weeks.
Where we started, and where we are going
New shingles, underlayment, flashing and eavestroughs on Building A, as the 2024 study planned. The roof was at the end of its life and had started to leak at the north parapet.
Things still to work out
Can the stairwell skylight be replaced while the crew is up there?
What we know now
Will owners need to move anything off their balconies? Only the top-floor owners, for two days while the edge is done. Hometime will post a notice a week before. · October 26, 2026
Cost
Planned cost (from the 2024 study): $181,350
Spent so far (as of November 13, 2026): $96,480
Elevator door operator replacement
Hometime is working out how to do this. Expected finish: January 2027.
1 of 4
Steps done
Hometime's plan has 4 steps; the key dates are shown below
2
Key dates
Shown below
0
Still to work out
Nothing outstanding
Key dates
Quote from the elevator contractorNovember 2, 2026· done
Install and test the new door operatorDecember 28, 2026· still open
Latest update
Hometime · November 4, 2026
The contractor's quote came in at $6,800, the same as the study. The deposit invoice is waiting for the board in Bill Approval.
Cost
Planned cost (from the 2024 study): $6,800
Parkade drain repair
This work is finished. On track
3 of 3
Steps done
Hometime's plan has 3 steps; the key dates are shown below
2
Key dates
Shown below
0
Still to work out
Nothing outstanding
Key dates
Camera inspection of the drainApril 24, 2025· done
Patch and seal the parkade floorMay 29, 2025· done
Expected finish: May 2025
Latest update
Hometime · June 4, 2025 On track
The drain is rebuilt and the floor is patched and sealed. The work came in under the estimate.
Where we started, and where we are going
The main parkade drain had collapsed under the ramp. It was dug out, rebuilt and the floor patched. Not in the study, so it was paid from the reserve as an unplanned repair.
What we know now
Is the second drain at the north wall in the same state? No. The camera showed it clear and sound. · April 25, 2025
Cost
Planned cost: $9,800
Spent so far (as of June 4, 2025): $9,215
Under by $585
What the words on this page mean
Planned
In the reserve fund plan for that year; nothing has been decided yet.
Planned 2026, now 2028
The study planned it for the first year; the plan now has it in the second.
Approved to go ahead
The board approved it from the plan and Hometime has started a project for it.
Underway
The work is happening.
Done
The work is complete.
Not in the study
A repair paid from the reserve fund that the study did not foresee.
Added after the study
An item Hometime added to the plan after the study was written.
Dropped
Taken out of the plan.
Combined with
Done together with another item, under that item's name.
Nothing planned
The study has no work in that year.
Reserve fund investments
The reserve fund's investments at market value on the date shown; money held in the fund's bank account is not included.
Study forecast
The study's forecast for that year as written, inflation included; it does not move when an item is moved, so it can differ from the plan table's Planned figure.
Contributions paid in
Money the owners paid into the reserve fund that year, through the condominium fees.
Closing balance
What the reserve fund holds at the end of that year; the study forecast is the study's figure, an actual comes from the books.
Planned cost
What the study allowed for the work, in the study's dollars.
Spent so far
What has been billed for the work so far, as of the date shown.
Under by / Over by
Spent so far compared with the planned cost; Under by appears once the work is finished or being checked.
Deciding whether to do it
The idea is on the table; nothing has been committed yet.
Getting started
The board has approved it from the reserve fund plan and Hometime is setting it up.
Working out how
Quotes, options and timing are being worked out. The dot is going up the hill.
Doing the work
The plan is set and the work is under way. The dot is coming down the hill.
Checking the work
The work is done and Hometime is confirming it was done right before closing it out.
Finished
Complete and closed.
Paused
On hold for now; it will pick up again later.
On track / Needs attention / Behind
Hometime's honest read of how it is going, updated with each report.
Key date
A date that matters to the board, such as a start, a deadline or a decision.